1, mixer should set in the flat position, with wooden pad front and rear wheels, so that the tire put overhead, order to avoid walking in when it is moving.
2, mixer should implement two leakage protection, work before the power supply is switched on, must be carefully examined, by the empty test switch that qualified before use. During the test run should test the suitability of mixing cylinder speed, generally, the proportion of empty vehicle speed (charging) slightly faster turn 2 ~ 3, such as the difference between the more proportion adjusting wheel and the drive wheel.
3, mixing drum rotation direction should be in line with the direction of the arrow, if not, should correct the motor wiring.
4, check the transmission clutch and brake is flexible and reliable, there is no damage to the wire rope, track pulley is good, there are no obstacles around and the lubrication of the parts, etc..
5, after the boot, often pay attention to the operation of each component of the mixer is normal. Stop, always check the mixer blade is bent, has knocked out or loose screws.
6, when the concrete mixing or is expected to stop 1H above, in addition to the rest of the material out of the net, the application of gravel and water into the drum, turn on the rotation, the mortar on the material cylinder after washing all discharged. There is no water in the barrel, so as to avoid the barrel and the blade rust. At the same time, we should clean up the ash outside the mixing drum to keep the machine clean.
7, after work and shut down, should pull the brake power, and lock the switch box, in order to ensure the safety.