1.Wipe the mixing pot and mixing blade with a damp cloth before testing.

2.Open the machine, pour the mixing water into the mixing pot, and add the weighed cement sample to the water to prevent water and cement from spilling.

3.Raise the agitator to the agitation position and start the mixer. Low speed 120s, stop for 15s. Scrape the blade and the cement on the wall into the middle of the pot, then stop at high speed for 120s.

4.Put the mixed cement paste into the consistency meter, and determine the standard consistency of the cement paste.

5.Initial and final setting times and stability tests were performed on standard consistency paste samples.

6.Record the start of watering time, wipe the mixing pot and mix the leaves.